Progress on Idyllwild Water District’s new 300,000 gallon storage tank in the Toll Gate zone continues. Here, one can see the rebar and poured concrete forming the tank’s foundation. Steel will be delivered this week and the tank welders will began constructing the tank on Monday, Oct. 7. General Manager Terry Lyons projects the welding will be completed in about two months if weather cooperates.