Idyllwild Water District directors, staff and company representatives spent most of Wednesday night’s meeting discussing a more than $5.7 million proposed project to upgrade IWD’s Wastewater Treatment Plant.

The board is considering the project because “the WWTP has been in operation for 50 years and now exceeds its designed life,” according to General Manager Leo Havener in a memo to the board. It was built in 1966 but did not go into operation until 1971, he wrote.

This plant is for the sewage system that only some IWD customers (about 587 households compared to about 1,670 current IWD households) use. All others use septic systems. IWD is the only water district in Idyllwild/Pine Cove offering sewer.

“Along with the WWTP exceeding its designed life span, the WWTP has no redundancy, has, on a few occasions, exceeded permit requirements, and has a lack of SCADA [Supervisory Control and Data Acquisition] controls,” wrote Havener, as the three primary WWTP facility needs. SCADA systems both control and monitor physical processes.

One concern repeatedly raised during discussions was storm surge — such as Feb. 14, 2019, when flash floods destroyed highways and roads on the Hill. WWTP Chief Plant Operator Fritz Wuttke said IWD’s WWTP permit may not exceed 75% of flow and it came close in February and March 2019 when an average of 168,000 gallons a day flowed into the 250,000-gallon WWTP tank. That equates to about 67%.

According to the California Rural Water Association’s subsidiary, Specialized Utility Services Program Inc. estimate, “The WWTP project planning phase is expected to last approximately 51 weeks and be completed in June 2022.”

The Sacramento company’s estimate breaks down as:

Mobilization/Demobilization $340,000 (management)

Planning, Design and Land $390,900 (electrical, structural, design plans and specs)

Sites and Facilities Project Work $857,500 (contractor work)

Secondary Treatment $1,506,200 (custom supplier package, or equal)

Electrical, Instrumentation $1,307,600

and Controls

Construction Management $302,600

and Inspection

Also, a Pre-Design Contingency at 30% is tacked on of $3,331,000 for a total estimated project cost of $5,766,000.

IWD directors heard from CRWA Field Engineer Nathan Thomas and Lead Project Facilitator Nicole Cook, both of whom also fielded a barrage of questions from directors — primarily concerning the project’s cost.

CRWA hopes to offset the cost with a Santa Ana Watershed Project Authority grant with a maximum award of $1 million. It also may gain funding through a combination of USDA Rural Utilities grant/long funds with the SAWPA matching funds; state-revolving funds; and private funding. This may also include loans.

But CRWA won’t know if funding will occur until it conducts two studies: Task Order 1 at $18,660 to determine IWD’s funding eligibility from various government sources for WWTP design and construction; and Task Order 2 of $260,970 for project management; a preliminary engineering report; a site survey; a geotechnical study; California Environmental Quality Act documents; and an electrical and SCADA preliminary design.

“The impact of $6 million is concerning,” IWD Vice President Peter Szabadi said when discussions that lasted more than an hour began.

Cook discussed many funding options — all of which must go through multiple stages and are not guaranteed — and advised that some of the funds take from 18 months to three years for approval, and at least one requires matching funds.

The suggestion of starting work before funding is fully secured resulted in Thomas commenting, “You want to get funding in place before beginning construction.”

Thomas pointed out as more directors emphasized their cost concerns that “everything costs double” as time is extending — that he’s projecting out the length of time of planning and construction, therefore, including $1.3 million “for everything I didn’t know.”

Later, he explained in more detail, “The $1.3 million is a contingency amount equal to 25 percent of the current project construction cost estimate. This is a typical and moderate amount of contingency value for a project at this stage of preliminary design and is specifically added to prevent the project cost from rising later when more information is available.

Similar Posts

  • Drought exacerbates fire season threats

    While an official forecast for this summer’s fire season is still several months away, the current situation and weather forecasts are foreboding, according to Tim Chavez, the Riverside County Fire Department’s Beaumont battalion chief. He spoke at the Feb. 13 Mountain Emergency Service Committee meeting. “Did the 2013 fire season end? No, we’re still staffed…

  • NEWS OF RECORD

    The Idyllwild Fire Protection District responded to these calls from Sunday to Saturday, Nov. 12 to 18. • Nov. 12 — EMS, transport. Palomar Rd. • Nov. 12 — EMS, treat & release. Dome Ln./Double View Dr. • Nov. 13 — EMS. Saunders Meadow Rd. • Nov. 13 — EMS, transport. Circle Dr. • Nov….

  • “Strictly Elvis UK” brings tour group to Idyllwild

    ‘Strictly Elvis UK” bills itself as “the UK’s largest Elvis fan organization.” The group is “Dedicated solely to keeping the legend of Elvis Presley alive and sharing his legacy with fans not only here in the UK but across the globe.” This week, founder David Wade brought 38 fans from overseas to the Idyllwild Area…

  • Hantavirus found in Sage

    Two deer mice collected last month near the Sage area southeast of Hemet have tested positive for Hantavirus. The California Department of Public Health confirmed the rodents that Riverside County Environmental Health officials submitted for testing on Dec. 15 and 28, 2011, were infected with the virus. Between 2001 and 2010, approximately 13 percent of…

  • No injuries in SUV rollover

    At left, according to California Highway Patrol Officer Ron Esparza, a solo-vehicle traffic collision occurred at about 3:30 p.m. Sunday, June 9. Amber Leigh Whitney-Krongaard, 23, of Idyllwild was driving her Ford Explorer on Highway 243 about a half mile north of Forest Service Vista Grande Guard Station at about 45 to 50 mph. As Krongaard approached a left-hand curve, her vehicle’s right wheels hit the dirt on the right side of the highway causing her to over correct the Explorer which crossed both lanes, hitting an embankment and flipping onto the passenger’s side. Krongaard was uninjured. Highway 243 was down to one lane of traffic for about one-and-a-half hours as Riverside County Fire Station 63, Forest Service, CHP and Idyllwild Garage cleared the scene.

  • Highway 243 Work Next Week

    This week’s update from Caltrans alerts motorists to delays on Highway 243 South of Idyllwild and North of Pine Cove. Highway 243 Work Scheduled for Week of November 3Crews will conduct multiple daytime projects on SR-243 between Mountain Center and Idyllwild from 8 a.m. to 4 p.m., Monday through Friday. Work will include upgrading storm…